Route 2 Project Updates Website
This website has been created to keep the public informed on Modot project JKU0049. Our goal is to provide clear, timely, and accessible information so residents, businesses, and travelers can plan ahead with confidence.
Here, you can view project updates, public notifications, traffic control maps, and the latest construction schedules. We encourage you to subscribe for updates to receive important notifications and progress reports directly.
Your awareness and cooperation are greatly appreciated as we work to complete this project as efficiently and safely as possible.
MoDot Project: JKU0049 // MoDot Call 250815-C03 // Lee's Summit Project Office
project info
The Missouri Department of Transportation (MoDOT) has contracted Emery Sapp & Sons, Inc (ESS) to complete Project JKU0049. This project consists of resurfacing approximately 14.7 miles of Route 2, extending from Independence Street in Harrisonville to Route ZZ in La Tour, MO, spanning both Cass County and Johnson County.
Construction is scheduled to begin May 4th at the intersection of South Independence Street, West South Street, and Route 2 in Harrisonville, with work progressing east toward La Tour. A pilot car operation will be in effect on Route 2 during construction. Barricades will be placed at adjoining Harrisonville neighborhoods to temporarily restrict access to Route 2 from these locations while construction is active through town. Vehicles already in the pilot car operation will still have the ability to access their respective neighborhoods. Please work with the posted flaggers while entering the work zone. **See the Barricade / Closure Plan(s) below to view the traffic control layout**
The initial phase of construction will involve placing a base (scratch) course in a continuous “racetrack” pattern from Harrisonville to La Tour and back. Following this, crews will install the final asphalt surface from Harrisonville to Route Z. During this phase, motorists should expect daily alternating lane closures.
Once paving operations reach Route Z, work will continue in a similar “racetrack” pattern between Route Z and La Tour. After paving is complete, crews will apply a final aggregate edge treatment along the outer edges of the roadway to complete the project.